HVAC systems’ operation is a critical requirement for maintaining adequate safe indoor air quality (IAQ), and ASHRAE developed guidance to help facility managers improve indoor air quality to slow the transmission of viruses via the HVAC system. Below is a checklist developed by Belimo, a leading provider of valves and actuators (and a product line that CM3 deploys) to help facility managers comply with that guidance.
Verify Indoor Air Quality
- Verify the differential pressure sensors or switches across your filter banks are operational and calibrated. Confirm the alarm limits in the BAS system are set to the differential pressure values indicating a clogged or dirty filter condition.
- With recommended requirements for air flushes and increased outdoor air intake, it is essential to inspect and confirm the operation and setpoints of your AHU freeze stats. Replace if faulty and add additional low temperature detection sensors/freeze stats for duct coverage as necessary.
- Verify the existing room and duct, temperature, humidity, and CO2 sensors are operational and calibrated. Replace failed sensors and add new sensors as required to meet suggested guidelines.
- Inspect and confirm the operation of the BAS humidity sensors. If using resistive type humidity and dew point sensors, consider changing to capacitive technology (CMOS) sensors, which are more accurate and not susceptible to drift. The updated ASHRAE 62.1 standard also requires systems to limit the indoor humidity to a maximum dew point of 60°F (15°C) during both occupied and unoccupied hours, whenever the outdoor air dew point is above 60°F (15°C). Belimo’s field selectable multi-sensors measure: temperature, RH, dew point, enthalpy, and absolute humidity.
- Verify the operation and calibration of the CO2 sensors associated with the Demand Control Ventilation (DCV) systems. Replace failed sensors and add sensors as necessary to meet the guidelines.
- Confirm the DCV systems operate to maintain maximum CO2 concentrations of 800-1000 ppm in occupied spaces.
- Are you using the latest technology in CO2 measurement? Dualchannel NDIR self-calibrating room and duct sensors meet the guidelines and ensure accuracy and reliability.
- Adding additional intake air to meet the new guidelines may cause building static pressure to change. Confirm static pressure is maintained at a positive pressure setpoint unless a specific zone calls for negative pressures like an isolation room.
Improve Occupant Safety
- Check the actuator for proper operation by verifying the damper is operating appropriately for on/off, floating, or modulating control.
- Verify the damper actuator meets the torque requirements.
- Is the actuator securely coupled to the drive shaft or linkage?
- Override the damper position with the DDC system to verify feedback is tracking the signal.
- Visually check the damper for proper movement.
- Command the damper to close fully. Excess air should NOT pass through the damper.
- Adjust the damper coupling or linkage if needed.
- Replace broken linkages.
- Replace damaged blades or edge seals and dry lubricate moving parts.
- Caulk damper frames to assure a tight connection to the structure.
Increase Ventilation
- Verify the damper movement.
- Modify the sequence of operations.
- Check the operation of the minimum outside air (MOA) adjustment.
- Check for failed components such as sensors, linkages, and actuators.
- Purge all spaces pre- and post-occupancy to flush the building with clean air.
- Change the start of operation hours (e.g., change 6 am start to 4 am) to provide a virus-free ambient air environment.
- When activated, the DCV C02 setpoint should be between 800-1000 ppm (during the COVID epidemic, ASHRAE recommends to disable demand ventilation control [DCV] and open outdoor air dampers 100% as outdoor and indoor conditions permit.). If an economizer is not functioning properly or capable of meeting ASHRAE recommendations, replace it with the Belimo ZIP Economizer
Ensure Proper Flow
- Verify control valves operate correctly by checking the valve stokes and ensure the selected signal, whether on/off, floating, or modulating, is working accurately.
- Verify the design flow requirement with a strap-on ultrasonic meter or with another measurement device.
- Override the valve position with the DDC system and verify that the feedback is tracking the signal.
- Change setpoint through the BMS or the thermostat to verify proper operation.
- Inspect the valve stem for leakage.
- Close the valve, and confirm no fluid is passing through the valve seat by using a measurement device.
- Make sure the direction of the flow is correct and not reversed.
- Ensure that you have enough pressure drop across the valve using differential pressure sensors or other measuring devices.
- Verify water quality
Big Picture
Maintaining optimal air flow, temperature and humidity can be complicated, and working with a professional is the best way to ensure your IAQ meets industry standards. With a range of HVAC, Mechanical and Retro-Commissioning services, CM3 can help.