Boyertown Area School District

Project Summary

An extensive, multi-year performance contract project for a large, suburban public school district covering portions of Berks and Montgomery Counties in southeastern Pennsylvania.  Owner benefits included enhanced occupant comfort, energy savings, solutions for failing systems, and standardization of equipment.

Performance Contract Services

  • Lighting Retrofit
  • Lighting Controls
  • Lamp/Ballast Disposal to EPZ Certified Site
  • Boiler Replacement
    • Earl Elementary
    • Pine Forge E.S.
    • New Hanover E.S.
  • Domestic Hot Water Repl.
  • Water Fountain Timers
  • Vending Machine Sensors

Key Information

Project Cost: $7.99 million

Financing: Municipal Lease / Purchase

Project Savings: $167,525/YR

Contract Terms: 15 Years

Facilities and Square Footage

Number of Buildings: 6

Square Footage of Project: S750,000

Description of Use: Schools and Administration

Duration: 32 Months